Difference between revisions of "Meeting 2023 07 19"
From Hall A Wiki
(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Update on BB GEMs) |
||
Line 13: | Line 13: | ||
=== Update on BB GEMs === | === Update on BB GEMs === | ||
− | * BB layer 0 is tripping with HV | + | * BB layer 0 is tripping with HV, plan: |
+ | ** Test HV board with HV (other GEM?) | ||
+ | ** Put resistive divider on GEM and check readback currents with HV | ||
=== Update on layers for GEn-RP === | === Update on layers for GEn-RP === |
Revision as of 20:51, 18 July 2023
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
GEM inventory for GEn-RP and GEp:
- Inventory and plan: [1]
- Workplan during SAD: [2]
- HV upgrade tracker: [3]
- GEM gas manager during SAD: [4]
Update on BB GEMs
- BB layer 0 is tripping with HV, plan:
- Test HV board with HV (other GEM?)
- Put resistive divider on GEM and check readback currents with HV
Update on layers for GEn-RP
- LV supply and plan for upcoming running
- Divider on EEL layer and plans for install
- GEn-RP design update