Line 26: | Line 26: | ||
* Update the documentation on the HV and LV operations (before beam) | * Update the documentation on the HV and LV operations (before beam) | ||
* GEM experts on call (setup before beam) | * GEM experts on call (setup before beam) | ||
− | * Clean up | + | * Clean up our areas (should start now, little by little) |
Revision as of 23:04, 26 March 2024
- SBS side LV:
- Joe to connect, instruct on controls (DONE!)
- Ellen to install some controller and readback (in progress, Ellen working with accelerator)
- Input the jumpers on the breakout panel (DONE!)
- Run the cables (in progress, Armen adding connectors)
- SBS GEMs:
- Install XW into stack (today?)
- Finish signal cabling (asap)
- Connect to HV patches (after HDMI cabling complete)
- reconnect gas to RP layers (after BB XY work?)
- techs to install final shielding blocks around the electronics hut
- BB GEMs:
- Upgrade the XY HV, re-install (would like to have SBS troubleshooting going on at the same time so as not to hold this up)
- Readout:
- Balance VTP fibers amongst crates to optimize (after GEMs are installed)
- Ensure that reboot/troubleshooting script works for all crates (DONE!)
- High voltage:
- Finish channels in GUI (DONE!)
- move HV to working reboot strip (done, but need to add to gui)
- finalize script for GUI upload of HV and operation (DONE!)
- Update the documentation on the HV and LV operations (before beam)
- GEM experts on call (setup before beam)
- Clean up our areas (should start now, little by little)