Line 13: | Line 13: | ||
* BB GEMs: | * BB GEMs: | ||
− | ** Upgrade the XY HV, re-install ( | + | ** Upgrade the XY HV, re-install (do we need to do this now?) |
* Readout: | * Readout: |
Revision as of 09:25, 27 March 2024
- SBS side LV:
- Joe to connect, instruct on controls (DONE!)
- Ellen to install some controller and readback (in progress, Ellen working with accelerator)
- Input the jumpers on the breakout panel (DONE!)
- Run the cables (in progress, Armen adding connectors)
- SBS GEMs:
- Install XW into stack (DONE!)
- Finish signal cabling (asap)
- Connect to HV patches (after HDMI cabling complete)
- reconnect gas to RP layers (after BB XY work?)
- techs to install final shielding blocks around the electronics hut
- BB GEMs:
- Upgrade the XY HV, re-install (do we need to do this now?)
- Readout:
- Balance VTP fibers amongst crates to optimize (after GEMs are installed)
- Ensure that reboot/troubleshooting script works for all crates (DONE!)
- High voltage:
- Finish channels in GUI (DONE!)
- move HV to working reboot strip (done, but need to add to gui)
- finalize script for GUI upload of HV and operation (DONE!)
- Update the documentation on the HV and LV operations (before beam)
- GEM experts on call (setup before beam)
- Clean up our areas (should start now, little by little)