* BB GEMs:
 
* BB GEMs:
 
** Check low-levels, cosmics (in progress)
 
** Check low-levels, cosmics (in progress)
 
* Readout:
 
** Balance VTP fibers amongst crates to optimize (maybe not needed)
 
  
 
* High voltage:
 
* High voltage:

Revision as of 09:16, 29 March 2024

  • SBS side LV:
    • Ellen to install some controller and readback (in progress)
  • SBS GEMs:
    • techs to install final shielding block around the electronics hut
    • Check low-levels, cosmics (in progress)
    • Techs to install scintillators today
  • BB GEMs:
    • Check low-levels, cosmics (in progress)
  • High voltage:
    • move HV to working reboot strip (done, but need add to documentation)
    • Add variables to accelerator to request for archiving (will do today)
  • Update the documentation on the HV and LV operations (before beam)
  • GEM experts on call (setup before beam)
  • Clean up our areas (in progress)