(Progress from this past week)
 
Line 6: Line 6:
 
----
 
----
 
=== Progress from this past week ===
 
=== Progress from this past week ===
 +
* DSG beginning the movement of the BB gas flowmeters to the SBS line.
 +
* Completed initial HV run up of all SBS layers with some issues identified (for the megger).
 
* L6M1 recovery with megger [https://logbooks.jlab.org/entry/4312487]
 
* L6M1 recovery with megger [https://logbooks.jlab.org/entry/4312487]
 
  
 
=== GEp preparations ===
 
=== GEp preparations ===

Latest revision as of 09:33, 17 July 2024

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Progress from this past week

  • DSG beginning the movement of the BB gas flowmeters to the SBS line.
  • Completed initial HV run up of all SBS layers with some issues identified (for the megger).
  • L6M1 recovery with megger [1]

GEp preparations

  • Our GEM task list is here: workplan
  • Remove layers, isolate shorted sectors, repair APVs as needed
  • Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
  • Install BB gas distribution from SBS line -- DSG will do this
  • Further calibrations of SBS gas mix
  • Install BB electronics crates and MPDs in new location
  • Prepare and install pixel layers
  • Repair/troubleshoot problematic CAEN crates -- DSG working on this
  • MPD testing and repair (we should do this now in test lab, who can coordinate?)

DAQ updates (Ben, Bryan, Alex)

  • Implement and test histogram method


https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues