Line 11: Line 11:
  
 
# Magnet Meeting summary
 
# Magnet Meeting summary
 +
<br> Went through the slides; there were a few comments about things that should be added and KK agreed to follow up with the engineer that had not sent comments.  Someone mentioned that we need to specify rad-hard epoxy.  Juliette will follow up with meetings with the engineers about the water-cooling and the concepts for the supports.  Roger mentioned that the calculations for the voltage and the power should be re-done for the new conceptual layout.<br>
 
# blocky actual inelastic plots
 
# blocky actual inelastic plots
 +
<br> Dustin showed the inelastic plots for the blocky actual model. 
 
# keep-out zones
 
# keep-out zones
 
# upstream torus layout
 
# upstream torus layout

Latest revision as of 14:00, 7 October 2010

Agenda

  1. Summary of August 31 Magnet Meeting - see summary talk
  2. New inelastic results for the "blocky actual" model - see Dustin's webpage
  3. defining keep-out zones - see elog 173, elog 175
  4. new results for the upstream torus layout - elog 172, elog 174
  5. Discussion
  6. Other items not mentioned above


Minutes

  1. Magnet Meeting summary


Went through the slides; there were a few comments about things that should be added and KK agreed to follow up with the engineer that had not sent comments. Someone mentioned that we need to specify rad-hard epoxy. Juliette will follow up with meetings with the engineers about the water-cooling and the concepts for the supports. Roger mentioned that the calculations for the voltage and the power should be re-done for the new conceptual layout.

  1. blocky actual inelastic plots


Dustin showed the inelastic plots for the blocky actual model.

  1. keep-out zones
  2. upstream torus layout
  3. Discussion
  4. Other items



Return to MOLLER at 11 GeV E09-005