Difference between revisions of "Commissioning Run Plan 2016"
From Hall A Wiki
(New page: For the Spring of 2016 assume: <ul> <li>Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration. <li>2.3 GeV @ 1st pass, 4.48 GeV @...) |
|||
Line 2: | Line 2: | ||
<ul> | <ul> | ||
<li>Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration. | <li>Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration. | ||
− | <li>2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass. No third pass beam in the Spring of 2016. | + | <li>2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass. |
+ | <li> <b>No third pass beam in the Spring of 2016</b>. | ||
<li> Angle restrictions with DVCS calorimeter in place: | <li> Angle restrictions with DVCS calorimeter in place: | ||
<ol> | <ol> |
Revision as of 13:57, 31 January 2016
For the Spring of 2016 assume:
- Maximum beam current = 20-25 μA but for short times it can go higher for boiling studies and BCM calibration.
- 2.3 GeV @ 1st pass, 4.48 GeV @ 2nd Pass, 8.84 GeV @ 4th pass, and 11.02 GeV @ 5th pass.
- No third pass beam in the Spring of 2016.
- Angle restrictions with DVCS calorimeter in place:
- HRS-BL: 17.9 to 45 degrees
- HRS-BR: 48.74 to 74.5 degrees