Difference between revisions of "APEX Experimental Readiness Review 2016"

From Hall A Wiki
Jump to: navigation, search
(Agenda (talks))
(Agenda (talks))
Line 19: Line 19:
 
|9:10  ||          Physics overview ([[Media:overview.pdf]])                        ||        Philip Schuster (15+5)               
 
|9:10  ||          Physics overview ([[Media:overview.pdf]])                        ||        Philip Schuster (15+5)               
 
|-
 
|-
|9:30  ||  '''Charge Item 1&5''': Design of the beam line items (excluding target)               ||      Robin Wines (20+10)         
+
|9:30  ||  '''Charge Item 1&5''': Design of the beam line items (excluding target) ([[Media:design.pdf]])            ||      Robin Wines (20+10)         
 
|-
 
|-
|10:00    ||  '''Charge Item 2&5''': Target design, thermal analysis and plans for the target  (including decommissioning) ||    Silviu Covrig (20+15)                                             
+
|10:00    ||  '''Charge Item 2&5''': Target design, thermal analysis and plans for the target  (including decommissioning) ([[Media:target.pdf]]) ||    Silviu Covrig (20+15)                                             
 
|-
 
|-
 
|10:35  ||    ''Break''            ||         
 
|10:35  ||    ''Break''            ||         
 
|-
 
|-
|10:50  ||  '''Charge Item 3''': Beam line magnetic shielding, beam analysis and commissioning           ||    Yves Roblin (15+10)             
+
|10:50  ||  '''Charge Item 3''': Beam line magnetic shielding, beam analysis and commissioning   ([[Media:beamline.pdf]])        ||    Yves Roblin (15+10)             
 
|-
 
|-
|11:15    ||  '''Charge Item 4''': Radiation level analysis                                       ||  Maduka Kaluarachchi (20+15)
+
|11:15    ||  '''Charge Item 4''': Radiation level analysis   ([[Media:radiation.pdf]])                                    ||  Maduka Kaluarachchi (20+15)
 
|-
 
|-
|11:50  ||  '''Charge Item 5''': Status of equipment (detectors)               ||    Gregg Franklin (15+5)     
+
|11:50  ||  '''Charge Item 5''': Status of equipment (detectors)     ([[Media:equipment.pdf]])          ||    Gregg Franklin (15+5)     
 
|-
 
|-
 
|12:10      ||  ''Working Lunch''
 
|12:10      ||  ''Working Lunch''
Line 35: Line 35:
 
|'''Afternoon'''
 
|'''Afternoon'''
 
|-
 
|-
|13:30    ||  '''Charge Items 6&7''': Equipment installation plan   ||    Jessie Butler (20+10)
+
|13:30    ||  '''Charge Items 6&7''': Equipment installation plan ([[Media:installation.pdf]]) ||    Jessie Butler (20+10)
 
|-
 
|-
|14:15    ||  '''Charge Item 8''': Responsibilities for carrying out each job   ||  Bogdan Wojtsekhowski (10+5)
+
|14:15    ||  '''Charge Item 8''': Responsibilities for carrying out each job ([[Media:respons.pdf]]) ||  Bogdan Wojtsekhowski (10+5)
 
|-
 
|-
|14:30    ||  '''Charge Item 9''': Documentation for all         ||  Rouven Essig (15+5)
+
|14:30    ||  '''Charge Item 9''': Documentation for all   ([[Media:doc.pdf]])      ||  Rouven Essig (15+5)
 
|-
 
|-
 
|14:50 ||  '''Charge Item 9''': Readiness of DAQ full rate capability ([[Media:APEX_DAQ.pdf]]) ||  Kalyan Allada (10+5)  
 
|14:50 ||  '''Charge Item 9''': Readiness of DAQ full rate capability ([[Media:APEX_DAQ.pdf]]) ||  Kalyan Allada (10+5)  
 
|-
 
|-
|15:05    ||  '''Charge Item 9''': High-rate events analysis || Seamus Riordan (10+5)  
+
|15:05    ||  '''Charge Item 9''': High-rate events analysis ([[Media:analysis.pdf]]) || Seamus Riordan (10+5)  
 
|-
 
|-
 
|15:20    ||    ''Closed Session''
 
|15:20    ||    ''Closed Session''

Revision as of 12:36, 21 March 2016

Overview

The A' Experiment (APEX)

Experimental Readiness Review 2016

Time and Location

  • Date: 07 April 2016 (Thursday)
  • Location: JLab CEBAF Room F224-F225

Agenda (talks)

Morning
8:30 Closed Session
9:00 Remarks from Chair and Charge Chair, ERR Committee
9:10 Physics overview (Media:overview.pdf) Philip Schuster (15+5)
9:30 Charge Item 1&5: Design of the beam line items (excluding target) (Media:design.pdf) Robin Wines (20+10)
10:00 Charge Item 2&5: Target design, thermal analysis and plans for the target (including decommissioning) (Media:target.pdf) Silviu Covrig (20+15)
10:35 Break
10:50 Charge Item 3: Beam line magnetic shielding, beam analysis and commissioning (Media:beamline.pdf) Yves Roblin (15+10)
11:15 Charge Item 4: Radiation level analysis (Media:radiation.pdf) Maduka Kaluarachchi (20+15)
11:50 Charge Item 5: Status of equipment (detectors) (Media:equipment.pdf) Gregg Franklin (15+5)
12:10 Working Lunch
Afternoon
13:30 Charge Items 6&7: Equipment installation plan (Media:installation.pdf) Jessie Butler (20+10)
14:15 Charge Item 8: Responsibilities for carrying out each job (Media:respons.pdf) Bogdan Wojtsekhowski (10+5)
14:30 Charge Item 9: Documentation for all (Media:doc.pdf) Rouven Essig (15+5)
14:50 Charge Item 9: Readiness of DAQ full rate capability (Media:APEX_DAQ.pdf) Kalyan Allada (10+5)
15:05 Charge Item 9: High-rate events analysis (Media:analysis.pdf) Seamus Riordan (10+5)
15:20 Closed Session
18:10 Close Out