(New page: ==== Procedure without Sieve-slit ==== * Time estimate: 2 hours * Take a run at the following kinematics without the sieve-slit collimator. * Start with initial right HRS spectrometer t...) |
(→Procedure without Sieve-slit) |
||
Line 3: | Line 3: | ||
* Take a run at the following kinematics without the sieve-slit collimator. | * Take a run at the following kinematics without the sieve-slit collimator. | ||
− | * Start with initial right HRS spectrometer tune with the | + | * Start with initial right HRS spectrometer tune with the new quad in place of right Q1. |
* If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure. | * If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure. | ||
− | * Electron rates assume | + | * Electron rates assume 7 carbon foils, 5 mSr acceptance, and 8% delta acceptance. |
* <b>A GMp expert will check the data quality and decide, if the right HRS tune needs to be adjusted to change the size of the acceptance.</b> | * <b>A GMp expert will check the data quality and decide, if the right HRS tune needs to be adjusted to change the size of the acceptance.</b> | ||
* This process will be repeated until the spectrometer tune is satisfactory.<br> | * This process will be repeated until the spectrometer tune is satisfactory.<br> |
Revision as of 11:45, 26 September 2016
Procedure without Sieve-slit
- Time estimate: 2 hours
* Take a run at the following kinematics without the sieve-slit collimator. * Start with initial right HRS spectrometer tune with the new quad in place of right Q1. * If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure. * Electron rates assume 7 carbon foils, 5 mSr acceptance, and 8% delta acceptance. * A GMp expert will check the data quality and decide, if the right HRS tune needs to be adjusted to change the size of the acceptance. * This process will be repeated until the spectrometer tune is satisfactory.
Ebeam [GeV] | P0 [GeV/c] | θe [deg] | Q2 [GeV2] | W [GeV] | Rate [Hz] at 5 μA | minutes for 29k events at 5 μA |
2.057 | 0.75 | 48.0 | 1.02 | 1.521 | 24.7 | 20 |
We want to take runs with the following Q1 currents:
- 0%: 159.75 A
- -6%: 150.165 A
- -5%: 151.7625 A
- -4%: 153.36 A
- -3%: 154.9575 A
- +5%: 167.7375 A