***3:00-3:15 Polarized 3He target (Cates) | ***3:00-3:15 Polarized 3He target (Cates) | ||
***3:15-3:45 WBS 2 – Neutron Form Factor: CDet (Monaghan) | ***3:15-3:45 WBS 2 – Neutron Form Factor: CDet (Monaghan) | ||
− | ***3:45-4:00 DAQ (Cisbani) | + | ***3:45-4:00 [https://hallaweb.jlab.org/wiki/images/e/ef/1611_SBS_DAQ_DOE_review_v3.pdf DAQ] (Cisbani) |
**Talks are due to post on Indico [https://www.jlab.org/indico/event/167/ official SBS review website] by noon Nov 2nd. | **Talks are due to post on Indico [https://www.jlab.org/indico/event/167/ official SBS review website] by noon Nov 2nd. | ||
* Background Material (provide to Review committee by Oct 24th) | * Background Material (provide to Review committee by Oct 24th) |
Revision as of 05:32, 27 October 2016
DOE 2016 review ( Nov 7 and 8th )
- Review will be in DOE Germantown.
- Charge letter for review.
- Panel List for review.
- Agenda. Conference room F-441 available earlier for waiting until meeting starts in room E-401.
- Dry run on Oct 27th from 1-5 in L102/104.
- Bluejeans +1.888.240.2560 https://bluejeans.com/612598535
- Talks
- 1 - 1:15 SBS Science Update and Overview (Ian Cloet )
- 1:15-1:30 SBS Project: Cost, Schedule and Management (Jones)
- 1:30-1:45 Talk Integration (Keppel)
- 1:45-2:15 talk WBS 2.2 & 2.3 – Beamline support, Electronics hut etc. (Wines)
- 2:15-2:45 WBS 3 – Proton Form Factor: GEM (Liyanage)
- 2:45-3:00 ECal (Riordan)
- 3:00-3:15 Polarized 3He target (Cates)
- 3:15-3:45 WBS 2 – Neutron Form Factor: CDet (Monaghan)
- 3:45-4:00 DAQ (Cisbani)
- Talks are due to post on Indico official SBS review website by noon Nov 2nd.
- Background Material (provide to Review committee by Oct 24th)
- PMP
- Monthly reports
- Previous DOE Review Reports
- 2013 Review:Cover letter,Excerpts from review,Final report,Indico webpage.
- 2014 review:Cover letter,Excerpts from review,Final report,Indico webpage.
- 2015 review:Cover letter,Excerpts from review,Final report,Indico webpage.
- Documents for DOE 2015 Review recommendations
- Recommendations tracker document
- Report on the thermal annealing test of prototype calorimeter.
- Report on that evaluates the ECal project including the technical feasibility of the annealing solution, and ECal project cost and schedule.
- Report on the C200 studies.
- A document detailing a design plan for scaling of the C200 to the final version of the calorimeter using thermal annealing.
- A document outlining information on implementation of the inal version of the calorimeter using thermal annealing, including analysis of potential failure modes. A schedule will be provided which states the time for decision for continuing with the thermal annealing option or switching to the UV curing option with the impact on schedule and cost of the switch.
- Report on trigger and DAQ. Need to send by Oct 3rd.
- Documents for DOE 2015 Review comments
- Note on the beam optics by Jay Benesch.
- Conceptual design report for the polarize 3He target
- Link to agenda and talks for the ECT Trento workshop: "Probing transverse nucleon structure at high momentum transfer" held April 2016.