== Minutes == | == Minutes == | ||
+ | |||
+ | * Task list/status | ||
+ | ** tolerance analysis (in progress) | ||
+ | ** material irradiation (new studies not begun) | ||
+ | ** radiation loads (new studies not begun) | ||
+ | ** impact of environmental variations (???) | ||
+ | ** floor loading (???) | ||
+ | ** fringe field impact (maps created, sims not run) | ||
+ | * Status of MIT/JLAB work | ||
+ | ** funding for new work | ||
+ | ** MIT/SBU spectrometer prototype fabrication status | ||
+ | *** a bulleted list of the objectives of prototype testing | ||
+ | *** a test plan and schedule for the above (so JLab folks should travel to observe some of the testing when appropriate) | ||
+ | ** a breakdown of the MIT request | ||
+ | *** coil tests | ||
+ | *** collimator/apparatus engineering | ||
+ | *** other activities | ||
+ | * Next meeting | ||
+ | |||
<br><br> | <br><br> |
Revision as of 13:48, 4 October 2017
Last meeting: Wednesday May 24, 2017 2:00pm ET
Agenda
- Task list/status
- tolerance analysis (in progress)
- material irradiation (new studies not begun)
- radiation loads (new studies not begun)
- impact of environmental variations (???)
- floor loading (???)
- fringe field impact (maps created, sims not run)
- Status of MIT/JLAB work
- funding for new work
- MIT/SBU spectrometer prototype fabrication status
- a bulleted list of the objectives of prototype testing
- a test plan and schedule for the above (so JLab folks should travel to observe some of the testing when appropriate)
- a breakdown of the MIT request
- coil tests
- collimator/apparatus engineering
- other activities
- Next meeting
Minutes
- Task list/status
- tolerance analysis (in progress)
- material irradiation (new studies not begun)
- radiation loads (new studies not begun)
- impact of environmental variations (???)
- floor loading (???)
- fringe field impact (maps created, sims not run)
- Status of MIT/JLAB work
- funding for new work
- MIT/SBU spectrometer prototype fabrication status
- a bulleted list of the objectives of prototype testing
- a test plan and schedule for the above (so JLab folks should travel to observe some of the testing when appropriate)
- a breakdown of the MIT request
- coil tests
- collimator/apparatus engineering
- other activities
- Next meeting