Link to all previous meetings: GMn GEM Commissioning Meeting


Kondo, Evaristo, Roberto, Siyu, Bogdan, Nilanga, Leo


Status of the INFN GEM Cosmic Stand (Roberto)

  • Provide the FNAL Test beam update.
  • They completed a scan of the multi-ZZ pattern PCB, along with gain and gap field scans.
  • Have other ZZ boards we want to test as well, including micromegas based detectors with ZZ readout.
  • Overall things are going well. They will report more in two weeks.

Status of the UVa GEM Cosmic Stand

  • They receive the new longer screws, will prepare them (cleaning etc ...) for assembly.
  • Will put the mock chamber together once more this week to check if gas leak issue is fixed with the longer screws