* just to give you a quick update about the EES production status.
 
* just to give you a quick update about the EES production status.
  - All the APV front-ends have been bonded and are on the way back to EES:
+
  - All the APV front-ends have been bonded and are on the way back to EES: they have plans to start testing from the 25 of February.  
they have plans to start testing from the 25 of February.  
+
 
  - I have to go there to help them to restart the test bench.  
 
  - I have to go there to help them to restart the test bench.  
 
  - Evaristo is very welcomed to come too.
 
  - Evaristo is very welcomed to come too.
  - The MPD production is still pending waiting for the FPGA procurement:
+
  - The MPD production is still pending waiting for the FPGA procurement: they claim to have found them and if everything goes well they can start assembling in 10 days from now.
they claim to have found them and if everything goes well they can start
+
assembling in 10 days from now.
+
 
  - I'll be in contact with them to get updates.
 
  - I'll be in contact with them to get updates.
  
 
=== AOB ===
 
=== AOB ===

Latest revision as of 09:52, 14 February 2019

GMn GEM commissioning Meetings: Thursday 9:00am - 10:00pm

Link to all previous meetings: GMn GEM Commissioning Meeting


Kondo, ... 

Update on UVa GEM commissioning (Kondo)

Update on MPD Low voltage PS (Siyu)

Update on Comic data (Tongtong)

Update on INFN GEM commissioning (Evaristo)

  • Short update from my side:
- new GEM foils from CERN going to be delivered in CT; possibly we found the
  way to avoid the custom delay we had in the past;
- two new modules assembled will be in Rome by next week;
- continue analysis of cosmic data (slightly improved software alignment and
  analysis software) and study data reduction in firmware.

Update on MPD electronics (Paolo)

  • just to give you a quick update about the EES production status.
- All the APV front-ends have been bonded and are on the way back to EES: they have plans to start testing from the 25 of February. 
- I have to go there to help them to restart the test bench. 
- Evaristo is very welcomed to come too.
- The MPD production is still pending waiting for the FPGA procurement: they claim to have found them and if everything goes well they can start assembling in 10 days from now.
- I'll be in contact with them to get updates.

AOB