Difference between revisions of "SoLID Weekly : Monday, May.20, 2019 9:30am EDT"

From Hall A Wiki
Jump to: navigation, search
(Minutes)
(Minutes)
Line 10: Line 10:
 
*JP: preR&D is not included in this duration.   
 
*JP: preR&D is not included in this duration.   
 
*:
 
*:
 +
 +
==Present==
 +
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen

Revision as of 09:46, 20 May 2019

Agenda

  • Discussion on SoLID cost estimation according to WBS (Work Breakdown

Structure)

  • Sub-system updates

Minutes

  • JP: Thia, Do you want to give a summary
  • Thia: I received LGC cost estimation. I think at this the point, the break down level makes sense for me, everything looks pretty good. However for a 5-year duration project, maybe it is worth to put the installation in the estimation.
  • Alexandre: Does this 5-year duration include 2-year preR&D and 3-year project?
  • JP: preR&D is not included in this duration.

Present

Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen