*On-going tasks
 
*On-going tasks
<nowiki>
+
**Network setup ( done )
Network setup ( done )
+
**Scaler crate setup (75 % - need put crate in / setup cpu )
Scaler crate setup (75 % - need put crate in / setup cpu )
+
**3 rd GEM VXS crate install router moved up ( 75%  )
3 rd GEM VXS crate install router moved up ( 75%  )
+
**need power and network in GEM bunker
need power and network in GEM bunker
+
**detector accounts setup
detector accounts setup
+
**boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
+
**detector cabling
detector cabling
+
**new MPD production - about to start - need to ship our FPGA to Paolo
new MPD production - about to start - need to ship our FPGA to Paolo
+
**MPD VTP readout - on-going in daq lab - being setup  in Hall A - need setup VTPs to boot
MPD VTP readout - on-going in daq lab - being setup  in Hall A - need setup VTPs to boot
+
**Bigbite - HCal trigger setup
Bigbite - HCal trigger setup
+
**TS setup - 0%
TS setup - 0%
+
**Beamline crate setup ( in scaler crate )  
Beamline crate setup ( in scaler crate )  
+
**HCAL cabling  
HCAL cabling  
+
**HCAL need power  
HCAL need power  
+
**Mark hodoscope trigger ?
Mark hodoscope trigger ?
+
**Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
+
*Outstanding issues
Outstanding issues
+
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
+
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
SD delay : still need 3 SDs ( Glasgow and INFN just requested quote )
+
**need to adjust for HCAL transit time with different PMTs
need to adjust for HCAL transit time with different PMTs
+
**status of cosmics paddles
status of cosmics paddles
+
**GEM fibers too short : 60 m ordered
GEM fibers too short : will order 60 m ordered
+
**15 bad MPDs
</nowiki>
+

Revision as of 10:22, 30 July 2021

  • On-going tasks
    • Network setup ( done )
    • Scaler crate setup (75 % - need put crate in / setup cpu )
    • 3 rd GEM VXS crate install router moved up ( 75% )
    • need power and network in GEM bunker
    • detector accounts setup
    • boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
    • detector cabling
    • new MPD production - about to start - need to ship our FPGA to Paolo
    • MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
    • Bigbite - HCal trigger setup
    • TS setup - 0%
    • Beamline crate setup ( in scaler crate )
    • HCAL cabling
    • HCAL need power
    • Mark hodoscope trigger ?
    • Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
  • Outstanding issues
    • 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
    • SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
    • need to adjust for HCAL transit time with different PMTs
    • status of cosmics paddles
    • GEM fibers too short : 60 m ordered
    • 15 bad MPDs