Line 16: Line 16:
 
**Mark hodoscope trigger ?
 
**Mark hodoscope trigger ?
 
**Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
 
**Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
 +
**LHRS fiber pull
 
*Outstanding issues
 
*Outstanding issues
 
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
 
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC

Revision as of 10:23, 30 July 2021

  • On-going tasks
    • Network setup ( done )
    • Scaler crate setup (75 % - need put crate in / setup cpu )
    • 3 rd GEM VXS crate install router moved up ( 75% )
    • need power and network in GEM bunker
    • detector accounts setup
    • boot VME controllers (GRINCH Hodo Shower , 2GEM crate up ~60 % controller booted - Bryan setting up as in TEDF - need setup MPD new controllers)
    • detector cabling
    • new MPD production - about to start - need to ship our FPGA to Paolo
    • MPD VTP readout - on-going in daq lab - being setup in Hall A - need setup VTPs to boot
    • Bigbite - HCal trigger setup
    • TS setup - 0%
    • Beamline crate setup ( in scaler crate )
    • HCAL cabling
    • HCAL need power
    • Mark hodoscope trigger ?
    • Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne
    • LHRS fiber pull
  • Outstanding issues
    • 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
    • SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
    • need to adjust for HCAL transit time with different PMTs
    • status of cosmics paddles
    • GEM fibers too short : 60 m ordered
    • 15 bad MPDs