Difference between revisions of "August 6th 2021"
From Hall A Wiki
Line 1: | Line 1: | ||
*Updates | *Updates | ||
**HCal | **HCal | ||
+ | ***still cabling - 9 bundles | ||
+ | ***32 cables additionnal + 32 spares channels | ||
+ | ***slack to be moved to HCAL side : difficult process on-going - might take a few days | ||
+ | ***hope to be done next week | ||
**Bigbite Shower | **Bigbite Shower | ||
+ | ***finished HV cables | ||
+ | ***working signal cables and trigger monitor | ||
+ | ***preshower finished on BB, shower cabling but others can use platform | ||
**Bigbite Hodoscope | **Bigbite Hodoscope | ||
+ | ***were waiting for cable trays - in place now - will start lying cables ADC and TDC | ||
+ | *** software progress | ||
+ | *** Level translator can be powered | ||
**GRINCH | **GRINCH | ||
+ | ***moved all slack near BigBite | ||
+ | ***HV cables : patch, can install long HV cables , HV cables at top of BB, need lift and will install TDC at same side | ||
**LHRS | **LHRS | ||
+ | ***almost ready, a few missing channels | ||
+ | ***Bob will help Ole in counting room - 2 weeks - might need more people | ||
**CDet | **CDet | ||
+ | ***student working on analysis with new students | ||
+ | ***working on resistors and taking data | ||
+ | *** 1.5 module left to go | ||
+ | *** some PMT ordered | ||
**GEM BB Hall A | **GEM BB Hall A | ||
+ | ***gas flowing on BB side | ||
+ | ***LV connection on-going | ||
+ | ***HV ready | ||
+ | ***checking connection : MPD fine, possibly one broken fiber | ||
+ | ***few spare lines avalaible | ||
+ | ***almost ready for readout | ||
+ | ***shielding : not solid plan for INFN in BigBite - could not run HV on chamber - making improvements adding kapton - ~2 days of trouble shooting | ||
+ | ***SSP readout almost done with CODA - should be avalaible at end of day - running on adaq1 | ||
+ | ***need to update SSP in Hall A | ||
**GEM INFN Test Lab | **GEM INFN Test Lab | ||
+ | ***J1 all shielding, J3 half installed | ||
+ | ***SSP readout in INFN all up to date and running | ||
**GEM UVA | **GEM UVA | ||
**Beamline | **Beamline | ||
+ | ***working on live plots for shift takers | ||
+ | ***hacsbc2 | ||
+ | ***run copy to SBS bunker | ||
**Helicity | **Helicity | ||
+ | ***helicity scaler installed on LHRS - was working in test setup | ||
+ | *** | ||
+ | **RF time | ||
+ | ***need to connect in LHRS and send copy to | ||
**HV | **HV | ||
+ | ***rpi online : GRINCH and shower should be ok | ||
+ | ***BB hodoscope need to be powered - same extension | ||
+ | ***MPOD installed - need to set it up on network | ||
+ | ***EPICS software avalaible for all | ||
+ | ***rpi17 and rpi18 off now - but can be turned one | ||
**Scalers | **Scalers | ||
− | *VME controllers | + | ***crate for scalers installed |
+ | ***working on software to handle different scalers | ||
+ | ***can turn on FADC scalers but depends on thresholds | ||
+ | ***scaler server run during run and between run | ||
+ | ***shower scalers can go in scaler crate if not there already | ||
+ | **VME controllers | ||
+ | ***all VME controllers booted for shower, hodoscope and GEM, GRINCH | ||
+ | |||
+ | |||
*On-going tasks | *On-going tasks | ||
− | **Network setup ( done ) | + | **Network setup ( done ) - SBS MPD side might need few cables |
− | **Scaler crate setup ( | + | **Scaler crate setup (50 % - Steve ) - need fix supply |
− | **3 rd GEM VXS crate install router moved up ( | + | **documentation of VME crate names to power cycle |
− | **need power and network in GEM bunker ( done ) | + | **3 rd GEM VXS crate install router moved up ( 50% ) |
− | **detector accounts | + | **need power and network in GEM bunker ( done ) - need connect computer |
+ | **detector accounts - will just use vncservers on different machines - | ||
**boot VME controllers (90 % done - need ask hostname TS crate ) | **boot VME controllers (90 % done - need ask hostname TS crate ) | ||
+ | **TS cables - all fibers plugged - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS | ||
**detector cabling | **detector cabling | ||
**new MPD production - about to start - FPGA shipped to Paolo | **new MPD production - about to start - FPGA shipped to Paolo | ||
− | **MPD VTP readout - on-going in daq lab | + | **MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link |
− | **MPD being setup in Hall A - need setup VTPs to boot | + | **MPD being setup in Hall A - need setup VTPs to boot - 10 gigE network plugged - will be able to test in Hall A - LV installed soon |
− | **setup portservers | + | **setup portservers : 1 4 port portserver for VTP, still need to set up a 8 port one and HCAL portserver |
− | **need to install remote switch for crate in bunker - rest are VXS or VME64 | + | **need to install remote switch for crate in bunker - rest are VXS or VME64 - |
− | **Bigbite - HCal trigger setup | + | **Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install |
− | **TS setup - | + | **TS setup - 50 % |
− | **Beamline crate setup ( in scaler crate ) | + | **Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup |
**HCAL cabling | **HCAL cabling | ||
− | **HCAL need power | + | **HCAL need power ( done, Berta ) |
**Mark hodoscope trigger ? | **Mark hodoscope trigger ? | ||
− | **Computer move to Hall A : sbsdaq1/2 tedbbdaq enpcamsonne | + | **Computer move to Hall A : sbsdaq1/2 tedbbdaq (done ) enpcamsonne ( will move next week ) |
− | **LHRS fiber pull | + | **LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run |
− | + | **BPM/BCM cables SBS weldment ( will do next week ) | |
*Outstanding issues | *Outstanding issues | ||
− | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC | + | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done ) |
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) | **SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) | ||
**need to adjust for HCAL transit time with different PMTs | **need to adjust for HCAL transit time with different PMTs | ||
**status of cosmics paddles ( installed by Bogdan ) | **status of cosmics paddles ( installed by Bogdan ) | ||
− | **GEM fibers too short : | + | **GEM fibers too short : Mark will order parts |
− | **15 bad MPDs | + | **15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand |
+ | ***APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir ) | ||
+ | **GEM fiber possibly bad | ||
+ | **GEM HV IP need setup ( Alex ) |
Latest revision as of 11:36, 6 August 2021
- Updates
- HCal
- still cabling - 9 bundles
- 32 cables additionnal + 32 spares channels
- slack to be moved to HCAL side : difficult process on-going - might take a few days
- hope to be done next week
- Bigbite Shower
- finished HV cables
- working signal cables and trigger monitor
- preshower finished on BB, shower cabling but others can use platform
- Bigbite Hodoscope
- were waiting for cable trays - in place now - will start lying cables ADC and TDC
- software progress
- Level translator can be powered
- GRINCH
- moved all slack near BigBite
- HV cables : patch, can install long HV cables , HV cables at top of BB, need lift and will install TDC at same side
- LHRS
- almost ready, a few missing channels
- Bob will help Ole in counting room - 2 weeks - might need more people
- CDet
- student working on analysis with new students
- working on resistors and taking data
- 1.5 module left to go
- some PMT ordered
- GEM BB Hall A
- gas flowing on BB side
- LV connection on-going
- HV ready
- checking connection : MPD fine, possibly one broken fiber
- few spare lines avalaible
- almost ready for readout
- shielding : not solid plan for INFN in BigBite - could not run HV on chamber - making improvements adding kapton - ~2 days of trouble shooting
- SSP readout almost done with CODA - should be avalaible at end of day - running on adaq1
- need to update SSP in Hall A
- GEM INFN Test Lab
- J1 all shielding, J3 half installed
- SSP readout in INFN all up to date and running
- GEM UVA
- Beamline
- working on live plots for shift takers
- hacsbc2
- run copy to SBS bunker
- Helicity
- helicity scaler installed on LHRS - was working in test setup
- RF time
- need to connect in LHRS and send copy to
- HV
- rpi online : GRINCH and shower should be ok
- BB hodoscope need to be powered - same extension
- MPOD installed - need to set it up on network
- EPICS software avalaible for all
- rpi17 and rpi18 off now - but can be turned one
- Scalers
- crate for scalers installed
- working on software to handle different scalers
- can turn on FADC scalers but depends on thresholds
- scaler server run during run and between run
- shower scalers can go in scaler crate if not there already
- VME controllers
- all VME controllers booted for shower, hodoscope and GEM, GRINCH
- HCal
- On-going tasks
- Network setup ( done ) - SBS MPD side might need few cables
- Scaler crate setup (50 % - Steve ) - need fix supply
- documentation of VME crate names to power cycle
- 3 rd GEM VXS crate install router moved up ( 50% )
- need power and network in GEM bunker ( done ) - need connect computer
- detector accounts - will just use vncservers on different machines -
- boot VME controllers (90 % done - need ask hostname TS crate )
- TS cables - all fibers plugged - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS
- detector cabling
- new MPD production - about to start - FPGA shipped to Paolo
- MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link
- MPD being setup in Hall A - need setup VTPs to boot - 10 gigE network plugged - will be able to test in Hall A - LV installed soon
- setup portservers : 1 4 port portserver for VTP, still need to set up a 8 port one and HCAL portserver
- need to install remote switch for crate in bunker - rest are VXS or VME64 -
- Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install
- TS setup - 50 %
- Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup
- HCAL cabling
- HCAL need power ( done, Berta )
- Mark hodoscope trigger ?
- Computer move to Hall A : sbsdaq1/2 tedbbdaq (done ) enpcamsonne ( will move next week )
- LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run
- BPM/BCM cables SBS weldment ( will do next week )
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done )
- SD delay : still need 2 SDs ( Glasgow and INFN just requested quote )
- need to adjust for HCAL transit time with different PMTs
- status of cosmics paddles ( installed by Bogdan )
- GEM fibers too short : Mark will order parts
- 15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand
- APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir )
- GEM fiber possibly bad
- GEM HV IP need setup ( Alex )