Difference between revisions of "Meeting 2022 09 21"
From Hall A Wiki
(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
(→Near term work plan) |
||
Line 7: | Line 7: | ||
=== Near term work plan === | === Near term work plan === | ||
− | * see the GEM commissioning run plan for GEn-II here: [https://docs.google.com/spreadsheets/d/1ONOpMdQAgFz6FKP5G605jyuHiWJ1Sv1HHhwWhHg7GnI/edit#gid=0] | + | * see the GEM commissioning run plan for GEn-II here: [https://docs.google.com/spreadsheets/d/1ONOpMdQAgFz6FKP5G605jyuHiWJ1Sv1HHhwWhHg7GnI/edit#gid=0] [https://hallaweb.jlab.org/wiki/index.php/File:0921.pdf] |
Latest revision as of 11:09, 21 September 2022
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
- HV efficiency scans with beam
Update on BB GEMs
Update on INFN GEM layers for GEn-RP
Update on UVa GEM layers for GEn-RP
- Update on the SBS gas system
- Update on repositioning the scintillators
Update monitoring with new GEMs in GEn-RP
- Online monitoring and SBS-offline preparation for GEn-II
DAQ updates (Ben, Bryan, Alex)
- SBS DAQ integration to GEn-II