Line 3: Line 3:
  
 
* SBS GEMs:
 
* SBS GEMs:
** techs to install final shielding block around the electronics hut  
+
** techs to install final shielding block around the electronics hut (status?)
** Finish cabling, low level testing, cosmics (in progress)
+
** Cosmics (in progress)
  
 
* BB GEMs:
 
* BB GEMs:
** Finish cabling, low level testing, cosmics (in progress)
+
** Cosmics (in progress)
  
* Update the documentation on the HV and LV operations (before beam)
+
* Update the documentation on the HV and LV operations (in progress)
* GEM experts on call (in progress)
+
* Update the GEM reset GUI
* Clean up our areas: move our stuff out of the Hall (in progress)
+
* GEM experts on call (please sign up!)
* Update channels in the alarm handler
+
* Clean up our areas: move our stuff out of the Hall (done?)
* High voltage cables?!
+
* Update channels in the alarm handler (status?)
 +
* High voltage cables?! (status/tests?)

Revision as of 04:55, 9 April 2024

  • SBS side LV:
    • Ellen to network for browser access (in progress)
  • SBS GEMs:
    • techs to install final shielding block around the electronics hut (status?)
    • Cosmics (in progress)
  • BB GEMs:
    • Cosmics (in progress)
  • Update the documentation on the HV and LV operations (in progress)
  • Update the GEM reset GUI
  • GEM experts on call (please sign up!)
  • Clean up our areas: move our stuff out of the Hall (done?)
  • Update channels in the alarm handler (status?)
  • High voltage cables?! (status/tests?)