(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...")
 
(DAQ updates (Ben, Bryan, Alex))
 
Line 24: Line 24:
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
=== DAQ updates (Ben, Bryan, Alex) ===
 
* Implement and test histogram method
 
* Implement and test histogram method
 +
 +
 +
https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues

Latest revision as of 10:28, 5 June 2024

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


GEp preparations

  • De-cable SBS GEMs -- done!
  • De-cable BB GEMs -- done!
  • Move GEMs into their respective new frames (front and back tracker) -- LOTO delay
  • Remove layers, isolate shorted sectors, repair APVs as needed
  • Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
    • We should make the cables in the meantime
  • Install BB gas distribution from SBS line -- DSG will do this
  • Further calibrations of SBS gas mix
  • Install BB electronics crates and MPDs in new location
  • Prepare and install pixel layers
  • Repair/troubleshoot problematic CAEN crates -- DSG will do this (meeting with them today)
  • Move the GEMs into place on SBS
  • Cable all GEMs
  • Readout and troubleshoot
  • MPD testing and repair (we should do this now in test lab, who can coordinate?)

DAQ updates (Ben, Bryan, Alex)

  • Implement and test histogram method


https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues