Difference between revisions of "Meeting 2024 07 10"
From Hall A Wiki
(Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...") |
|||
Line 5: | Line 5: | ||
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs! | Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs! | ||
---- | ---- | ||
+ | <span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> | ||
+ | |||
+ | Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.php/GMn_GEM_Commissioning_Meeting GMn GEM Commissioning Meeting] | ||
+ | |||
+ | Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs! | ||
+ | ---- | ||
+ | === Progress from this past week === | ||
+ | * | ||
+ | * | ||
+ | * | ||
+ | |||
=== GEp preparations === | === GEp preparations === | ||
* Our GEM task list is here: [https://docs.google.com/spreadsheets/d/1yrdQfzWGnXn4D0n08NTdxoW9Yv4hdbTwirPR2SO7UCM/edit?usp=sharing workplan] | * Our GEM task list is here: [https://docs.google.com/spreadsheets/d/1yrdQfzWGnXn4D0n08NTdxoW9Yv4hdbTwirPR2SO7UCM/edit?usp=sharing workplan] |
Revision as of 15:35, 8 July 2024
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Progress from this past week
GEp preparations
- Our GEM task list is here: workplan
- Remove layers, isolate shorted sectors, repair APVs as needed
- Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
- Install BB gas distribution from SBS line -- DSG will do this
- Further calibrations of SBS gas mix
- Install BB electronics crates and MPDs in new location
- Prepare and install pixel layers
- Repair/troubleshoot problematic CAEN crates -- DSG working on this
- MPD testing and repair (we should do this now in test lab, who can coordinate?)
DAQ updates (Ben, Bryan, Alex)
- Implement and test histogram method