(Suggested order of work)
(Suggested order of work)
 
Line 24: Line 24:
 
* Fabricate remaining LV cables
 
* Fabricate remaining LV cables
 
* Upgrade the BB XY layer to SHV (test it)
 
* Upgrade the BB XY layer to SHV (test it)
 +
* Repair/replace L6 modules, install as last layer in Back Tracker, until EEL layer is ready
 
* Move a BB MPD crate near the working layers new LHRS, cable up a layer for readout
 
* Move a BB MPD crate near the working layers new LHRS, cable up a layer for readout
 
* For cosmics, bring bars (HV+signal cables) to table and make a readout trigger. Work with techs to bring out 1 layer at a time?
 
* For cosmics, bring bars (HV+signal cables) to table and make a readout trigger. Work with techs to bring out 1 layer at a time?

Latest revision as of 11:04, 24 July 2024

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


Progress from this past week

  • DSG beginning the movement of the BB gas flowmeters to the SBS line.
  • Testing of BB layers HV

GEp preparations

  • Our GEM task list is here: workplan
  • Remove layers, isolate shorted sectors, repair APVs as needed
  • Joe B will add LV inputs for new GEMs in the stack, we will need to make those cables (4 more layers)
  • Install BB gas distribution from SBS line -- DSG will do this
  • Further calibrations of SBS gas mix
  • Install BB electronics crates and MPDs in new location
  • Prepare and install pixel layers
  • Repair/troubleshoot problematic CAEN crates -- DSG working on this
  • MPD testing and repair (we should do this now in test lab, who can coordinate?)

Suggested order of work

  • Move layers into front and back tracker
  • Fabricate remaining LV cables
  • Upgrade the BB XY layer to SHV (test it)
  • Repair/replace L6 modules, install as last layer in Back Tracker, until EEL layer is ready
  • Move a BB MPD crate near the working layers new LHRS, cable up a layer for readout
  • For cosmics, bring bars (HV+signal cables) to table and make a readout trigger. Work with techs to bring out 1 layer at a time?
    • Option 2: Can we move stack to be near RHRS, we can access all gas lines, setup readout, LV etc. Setup scintillators around the stack and run for a longer period.
    • Option 3: Or do we want to do this putting the stack on the platform? Harder to repair.
    • Option 4: Stacks between LHRS and DAQ, re-run all the cables, MPDs, gas lines, etc. Possibly readout few layers at a time.
  • Other work, setup gas flow in EEL to chamber. Finish HV upgrade & test.

DAQ updates (Ben, Bryan, Alex)

  • Implement and test histogram method


https://redmine.jlab.org/projects/sbs-daq-gep-gems/issues