Polhe3 meeting 20111005
From Hall A Wiki
- progress
- new cell and oven bottom piece (zhiwen)
- The first cell has not been filled due to some complications in the gas system. The second cell is not delivered and won't be until the first one is filled. Alan is working on oven bottom piece.
- temperature optimization test (all)
- new cell and oven bottom piece (zhiwen)
- Calendar
timeline | Tasks | To be done by | status |
---|---|---|---|
new cell and oven bottom piece | |||
10/05-10/19 | receiving and check fitting | all | |
convection flow study | |||
10/05-10/19 | make a zapper coil or a pair of coils to confine field better | Chunhua | |
10/05-10/19 | do calibration on old and new RTD. connect RTD readout/control in labview | Jie | |
diffusion mode measurement | |||
10/05-10/19 | do the test | all | |
10/05-10/19 | improve analysis, check fitting with error estimation and prepare plots for a note. | Chunhua | |
pulse NMR | |||
10/05-10/19 | pNMR setup and test | Jie | |
10/05-10/19 | find or make coil and test it with capacitor matchbox | Chunhua |