Proton Elastic Kinematics

* If you need to increase the spectrometer momentum setting, make sure you cycle Q2 and Q3 as per the cycling procedure.
* Elastic electron rates assume 20 μA on 15 cm LH2 target, 5 mSr acceptance.
* Use the following prescale factors: ps1=1, ps2=1, ps3=1, ps8=100. All other triggers should have zero prescale factor. 
* A GMp expert will check the data quality.
  • 2nd Pass (Ebeam = 4.5 GeV) Time estimate: 12 hours @ 20 μA
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA hours at 20 μA
15 cm LH2 2 x 2 mm2 4.481 1.547 52.91 5.5 1.4 7 (for 35k events)
Optics Off 4.481 1.547 52.91 5.5 0.23 0.5 (for 400 events)
Optics% Off 4.481 0.85 52.91 3.0 4.2 at 10 μA 0.5 (for 7.5k events)at 10 μA</)</td>
 </tr>	
15 cm Dummy#</td> 2 x 2 mm2</td> 4.481</td> 1.547</td> 52.91</td> 5.5</td> 0.26</td> 4 (for 3.7k events)</td>
 </tr>	

</table>

% <b>Alternative kinematics for pointing run.
# Take Al dummy data only if time permits.


  • 4th Pass (Ebeam = 8.8 GeV) Time estimate: 22 days @ 20 μA
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA days at 20 μA
15 cm LH2 2 x 2 mm2 8.841 2.101 48.74 12.65 0.018 21 (for 32k events)
15 cm Dummy 2 x 2 mm2 8.841 2.101 48.74 12.65 ----


  • 5th Pass (Ebeam = 11.0 GeV) Time estimate: 39 days @ 20 μA
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA days at 20 μA
15 cm LH2 2 x 2 mm2 11.021 2.204 48.74 16.54 0.003 38 (for 10k events)
15 cm Dummy 2 x 2 mm2 11.021 2.204 48.74 16.54 ----


  • 2nd Pass (Ebeam = 4.5 GeV) Time estimate: 7 hours @ 20 μA
Target Raster Ebeam [GeV] P0 [GeV/c] θe [deg] Q2 [GeV2] Electron Rate [Hz] at 20 μA hours at 20 μA
15 cm LH2 2 x 2 mm2 4.481 1.706 48.75 5.21 2.4 4 (for 35k events)
15 cm Dummy 2 x 2 mm2 4.481 1.706 48.75 5.21 0.4 2.5 (for 3.6k events)