SoLID Weekly : Monday, May.13, 2019 9:30am EDT

From Hall A Wiki
Revision as of 10:12, 13 May 2019 by Tianye (Talk | contribs) (Minutes)

Jump to: navigation, search

Agenda

  • Discussion on SoLID cost estimation according to WBS (Work Breakdown

Structure)

  • Sub-system updates

Minutes

  • JP: Based on the Moller review feedback, we need to prepared more detail cost estimation. JP shows a table for the subsystem cost estimation, and he will send out this form to the person in charge of the subsystems.
  • Paul: Things is changing by the time, so how do we handle the costing changing?
  • JP: small change is normal, if it is a large change we need to discuss with the committee.
  • Nilanga: Is the review is scheduled?

JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September.

  • Nilanga: We should add the overhead, isn't?
  • JP: You just need to add your numbers. Jlab will use the average cost which includes everything you need.

Present

Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen