Response to DOE 2014 review report

  1. Final report from DOE Nov 2014 SBS review.
  2. DOE Nov 2014 recommendations with responses. Initial response to the recommendations and comments.

DOE 2015 review

  • Draft agenda.
  • Initial Drafts due by October 21st for posting to wiki and overview by collaboration.
  • Dry run talks ( on Nov 5th) from 8:30-2 :
    • 8:30-8:50 SBS Science Update and Overview Talk (Wojtsekhowski)
    • 8:50-9:20 SBS Project: Cost, Schedule and Management (Jones)
    • 9:20-9:40 Dependency overview (Keppel)
    • WBS 1 – SBS Basic: Magnet and Infrastructure (Wines)
    • WBS 2 – Neutron Form Factor: talk CDet (Khandaker)
    • WBS 3 – Proton Form Factor: GEM (Liyanage)
    • DAQ VME and Fastbus Talk (Moffitt)
    • Background MC – all experiments (Riordan)
    • Breakout: Dependencies
      • Polarized 3He target (Cates)
      • HCal ( Franklin)
      • ECal (Riordan)
      • GRINCH (Averett)