  • SBS side LV:
    • Ellen to install some controller and readback (in progress)
  • SBS GEMs:
    • techs to install final shielding blocks around the electronics hut
    • Check low-levels, cosmics
    • Techs to install scintillators next week
  • BB GEMs:
    • Check low-levels, cosmics
  • Readout:
    • Balance VTP fibers amongst crates to optimize (after GEMs are installed)
  • High voltage:
    • move HV to working reboot strip (done, but need to add to gui)
    • Add variables to accelerator to request for archiving
  • Update the documentation on the HV and LV operations (before beam)
  • GEM experts on call (setup before beam)
  • Clean up our areas (in progress)