October 24, 2011 Saftey/Readiness Review
JLab F113, 1:00-5:00 pm
Topic | Presenter |
---|---|
Intro | J. P. Chen |
Beamline | T. Michalski |
Beamline Commissioning | Y. Roblin (or designate) |
Target | C. Keith |
Hall A Mechanical Structures | E. Folts |
New Equipment & Structures | R. Wines |
Radiation | P. Degtiarenko (or designate) |
Experiment Preparation | K. Slifer |
In addition to demonstrating overall safety and readiness, the committee has asked us to address these questions
Note to Presenters: Please post all material at : /u/group/halla/www/hallaweb/html/experiment/g2p/meetings/safety_102411
They will then be viewable here
HDICE committee charge for reference