Short Optics Plan 'Define the following jobs: A. Acceptance calib, sieve out, raster on and off (large C12, no LHe) B. Delta scan, (sieve in, C12, no LHe) C. Beam persion scan (Sieve in, large C12, no LHe, 8 points on x,y axis and 4 additional points at corner) D. Pointing (Sieve in, CH2, need refill LHe)

'Here is the summary of all optics: 1. 0T @ 2.257: Do A, move sieve in, do B and C(12 points), refill LHe do D. At the end take elastic NH3 data to check NH3 thickness. When finish: move sieve out; Ramp field up to 2.5T; Drian LHe

2. 2.5T|90deg @ 2.257: Do A, move sieve in, do B and C(12 points), refill LHe do D When finish: Ramp field up to 2.5T; Drian Lhe out

3. 5.01T|6deg @ 2.257: Do B and C(8 points), refill LHe do D.

4. 2.5T|90deg @ 1.706: Do A, move sieve in, do B and C(8 points), refill LHe do D When finish: Rotate target field to 6 deg; Ramp up to 5.01T; Drian Lhe out

5. 5.01T|6deg @ 1.706: Do B and C(8 points), refill LHe do D When finish: Move sieve out; Rotate target field to 90 deg; Ramp up to 5.01T; Drain LHe out

6. 5.01T|90deg @ 2.257: Do A, move sieve in, do B and C(8 points), refill LHe do D When finish: Turn off target field; Drian Lhe, move sieve out.

7. 0T @ 1.159: Do A, move sieve in, do B and C(8 points), refill LHe do D. At the end take elastic NH3 data to check NH3 thickness. When finish: move sieve out; Ramp field up to 2.5T; Drian Lhe out

8. 2.5T|90deg @ 1.159: Do A, move sieve in, do B and C(8 points), refill LHe do D When finish: Ramp field up to 5.01T; Drian Lhe out

9. 5.01T|6deg @ 1.159: Do B and C(8 points), refill LHe do D




For commissioning: