GMp Tasks and pending issues

From Hall A Wiki
Revision as of 17:08, 25 September 2012 by Camsonne (Talk | contribs) (New page: Back to DVCS Previous tables Task assignement August 15th 2010 Experiment tasks *scalers *sync check *HV *HRS calibration *Beamline cablibration *dead time *lumi {| align="le...)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Back to DVCS

Previous tables

Task assignement August 15th 2010

Experiment tasks

  • scalers
  • sync check
  • HV
  • HRS calibration
  • Beamline cablibration
  • dead time
  • lumi


Name Expertise Secondary expert Task list Completion level / Completed / Left to be done Estimated completion date Main task
Alexandre Camsonne ARS DAQ, Slow control, decoding, paperwork Trigger
 * ARS test readout
 * ARS final readout
 * Buffering test
 * DVCS HRS Trigger implementation
 * Test decoder
 *  Slow control LED 
 * Slow control current ADC
 * HRS integration
 * COO
 * ESAD
 * RSAD
 * TOSP
 * 100 % ( need implement checks and not working 100 % )
 * 60 % ( crates being added )
 * 90 % ( seems to work - need synch check )
 * 60% (  )
 * 70 % ( need implement checks - several ROCs)
 * 100 % ( hardware ok - need write C functions driver and ROOT interface )
 * 95 % ( Full test with calo )
 * 80% ( waiting for crates to be in HRS )
 * 90 % ( need edit files ) 
 * 30 % ( need adapt to DVCS )
 * 100 % ( Pavel waiting to send for signatures )
 * 0 % ( still not found old one )
 * NA
 * Aug 30 th
 * in progress 08/25/2010
 * 08/30/2010
 * 08/30/2010 
 * 08/25/2010 ( 1 day )
 * 08/30/2010 ( cabling needed )
 * when everything in HRS, no later than september
 * 08/25/2010
 * 08/30/2010
 * 09/5/2010
 * 09/01/2010 
Setup DVCS crates in HRS
Lumi Lumi

}