Thursday, Mar. 03: OWL Shift
From Hall A Wiki
Go back to Daily Run Plan Daily Run Plans
General considerations
- BTA: SL makes sure to submit his/her BTA successfully and be shown in HALOG
- Need shift crews for future
Specific mission
- Production Run
- Beam set up without Compton chicane for tonight (will try to set beam up with Compton chicane after RF recovery and BCM calibration tomorrow afternoon)
Upcoming event(Short Term)
- Note: MCC RF recovery (8:30-11:30AM, Thursday)
Access Wish List:(controlled access)
1/ Doug: Series of magnet measurement <: 1hr / no beam/ but beam permit
(a) He will start 8:30AM at MCC
(b) Expect to complete by 9:00AM (or whenever he finishes, he will notify us.)
->Then call MCC for controlled access (Are these highest priority ???)
2/ Andrew Lumanog: (Call 327-5523) : <1hr
3/ Dave/Greg: check Compton laser profile : <1hr
4/ Longwu/Thir: D1 BCM for RHRS
After RF recovery,
- Mar/03 BCM calibration (high beam current 30uA(60 ideal),FC, invasive Hall-D after RF recovery done (around noon)
-- Hall-D will be down for adding new diamond radiator (up to 8hrs): This is good chance for us to BCM calibration
- Detailed instructions
- If everything goes well, We come back to production run
Upcoming event(Long Term)
- Target boiling test
- Beam study (Thursday, 3/10)
BPM/Spot++ Check
- After beam lost for considerable time (like beam study, pass change,...)
- Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++