Thursday, Mar. 03: OWL Shift

From Hall A Wiki
Revision as of 20:46, 2 March 2016 by Parkkj (Talk | contribs)

Jump to: navigation, search

Go back to Daily Run Plan Daily Run Plans

General considerations

  • BTA: SL makes sure to submit his/her BTA successfully and be shown in HALOG
  • Need shift crews for future


Specific mission

  • Production Run
  • Beam set up without Compton chicane for tonight (will try to set beam up with Compton chicane after RF recovery and BCM calibration tomorrow afternoon)


Upcoming event(Short Term)

  • Note: MCC RF recovery (8:30-11:30AM, Thursday)

Access Wish List:(controlled access)
1/ Doug: Series of magnet measurement <: 1hr / no beam/ but beam permit
(a) He will start 8:30AM at MCC
(b) Expect to complete by 9:00AM (or whenever he finishes, he will notify us.)


->Then call MCC for controlled access (Are these highest priority ???)
2/ Andrew Lumanog: (Call 327-5523) : <1hr
3/ Dave/Greg: check Compton laser profile : <1hr
4/ Longwu/Thir: D1 BCM for RHRS

After RF recovery,

  • Mar/03 BCM calibration (high beam current 30uA(60 ideal),FC, invasive Hall-D after RF recovery done (around noon)

-- Hall-D will be down for adding new diamond radiator (up to 8hrs): This is good chance for us to BCM calibration

  • Detailed instructions

BCM DOC1DOC2

  • If everything goes well, We come back to production run


Upcoming event(Long Term)

  • Target boiling test
  • Beam study (Thursday, 3/10)


BPM/Spot++ Check

  • After beam lost for considerable time (like beam study, pass change,...)
  • Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++