Monday,Mar. 28: DAY Shift
From Hall A Wiki
Revision as of 14:38, 29 March 2016 by Parkkj (Talk | contribs) (New page: Go back to Daily Run Plan Daily Run Plans <b>currently</b> * MCC restore the beam Hall-A * Resolved all problems they mentioned in this morning (1st pass RF separator/ Moller Quad po...)
Go back to Daily Run Plan Daily Run Plans
currently
- MCC restore the beam Hall-A
- Resolved all problems they mentioned in this morning (1st pass RF separator/ Moller Quad power cycle/...)
BPM/Spot++ Check
- After beam lost for considerable time (like beam study, pass change,...)
- Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++