Response to DOE 2015 review report
- Cover letter for DOE Nov 2015 SBS review.
- Excerpts from DOE Nov 2015 SBS review.
- report from DOE Nov 2015 SBS review.
- DOE Nov 2015 recommendations with responses. Initial response to the recommendations and comments.
DOE 2016 review ( Nov 7 and 8th )
- Charge letter for review.
- Panel List for review.
- Agenda.
- Initial Drafts due by October 3rd for posting to wiki and overview by collaboration.
- Dry run talks sometime between Oct 17-28th. Talk are due to Review committee by Nov 3rd.
- Background Material (provide to Review committee by Oct 24th)
- PMP
- Monthly reports
- Previous DOE Review Reports
- 2013 Review:Cover letter,Excerpts from review,Final report,Indico webpage.
- 2014 review:Cover letter,Excerpts from review,Final report,Indico webpage.
- 2015 review:Cover letter,Excerpts from review,Final report,Indico webpage.
- Documents for DOE 2015 Review recommendations
- Recommendations tracker document
- Report on the thermal annealing test of prototype calorimeter.
- Report on that evaluates the ECal project including the technical feasibility of the annealing solution, and ECal project cost and schedule.
- Report on trigger and DAQ.
- Documents for DOE 2015 Review comments
- Note on the beam optics by Jay Benesch.
- Conceptual design report for the polarize 3He target
- Link to agenda and talks for the ECT Trento workshop: "Probing transverse nucleon structure at high momentum transfer" held April 2016.