GMn GEM commissioning Meetings: Thursday 9:00am - 10:00pm

Link to all previous meetings: GMn GEM Commissioning Meeting


Kondo, ... 

Update on UVa GEM commissioning (Kondo)

  • Short update
- HV test on N2 of the 4 modules of layer#2 done OK again see link: https://hallaweb.jlab.org/dvcslog/SBS/266

- Plan to do HV test of the GEMs or layer#1 on the cosmic stand again and then move layer#2 on the cosmic stand as well

- 34 UVa long cables for layer#2 + a set of MONO cables for one module delivered

- We will have to setup a standalone test bench of backplane + APVs before mounting on the chambers (see Siyu's slides)

- First versions of the backplanes support on the Alu frames 3D printed => Need small modifications about dimensions => second iteration underway

- Got long HV cables from Bogdan for the Clean room GEM layers 

- Need someone for the test of the divider and PMT for these modules with the help from Bogdan

- We start assembly of PREX GEMs (Siyu) => will keep us busy for the next 3 weeks => delay the UVa GEM layer assembly. 

Update from Siyu

Update from Tongtong and Malinga

Update on INFN GEM commissioning (Evaristo)

Update on MPD electronics (Paolo)

AOB