SoLID Weekly : Monday, May.13, 2019 9:30am EDT
From Hall A Wiki
Agenda
- Discussion on SoLID cost estimation according to WBS (Work Breakdown
Structure)
- Sub-system updates
Minutes
- JP: Based on the Moller review feedback, we need to prepared more detail cost estimation. JP shows a table for the subsystem cost estimation, and he will send out this form to the person in charge of the subsystems.
- Paul: Things is changing by the time, so how do we handle the costing changing?
- JP: small change is normal, if it is a large change we need to discuss with the committee.
- Nilanga: Is the review is scheduled?
JP: We are looking for August, but it is quite difficult based on the current information. It is probably early September.
- Nilanga: We should add the overhead, isn't?
- JP: You just need to add your numbers. And Jlab will use the average cost which includes everything you need.
- Zhiwen: For the graduate student, should we use 1.5 labor.
- JP: we will do individual labor estimation.
Present
Alexandre, JP, Haiyan, Paul, Nilanga, Seamus, Guannan, Ye, Junqi, Rich, and Zhiwen