2009 Holiday Schedule

From Hall A Wiki
Revision as of 18:12, 10 December 2008 by Yqiang (Talk | contribs) (Jan 7, Tuesday, 2009 - Beam start)

Jump to: navigation, search

Dec 22, Monday, 2008

  1. Polarization calibration: EPR, NMR, Temperature
  2. Polarization loss test
  3. HRS Magnet effect test: requires turning ON/OFF magnets for a couple of times
  4. Check laser spectrum with cell
  5. Cool down oven

Dec 23, Tuesday, 2008

  1. RadCon surveys the target enclosure
  2. remove the 3He cell and target ladder
  3. Install water cell
  4. Prepare for water calibration: require turning off pump, other environment noise.
  5. Water calibration

Dec 24, Wednesday, 2008

  1. Water calibration

Dec 25, Thursday, 2008 - Jan 4, Sunday, 2009

  1. Compass measurement: Transverse, Vertical (optional)

Jan 5, Monday, 2009

  1. Compass survey
  2. Install 3He cell and ladder

Jan 6, Tuesday, 2009

  1. Target Survey

Jan 7, Wednesday, 2009 - Beam start

  1. Laser check
  2. Pumping
  3. Polarization calibration