Meeting 2022 06 01
From Hall A Wiki
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
Contents
Near term work plan
- See installation plan for SBS here: plan
- Installation of HV dividers on BB: work plan
- Thoughts on special run requests during GEn:
- Luminosity studies (Nilanga)
- Full readout studies for negative pulse studies and etc (Sean)
Update on INFN GEM layers for GEn-RP
- Ran up HV on old dividers in the inline stack
Update on UVa GEM layers for GEn-RP
- Pre-move-to-hall Summary update for the Status of the GEM modules/layer in EEL125.
- Latest DAQ tests DAQ rate tests summary in EEL 125
Update on BB GEMs
Common Mode Algorithms
DAQ updates (Ben, Bryan, Alex)
- schematic of setup?
- FIR filter?
- Update on: need 2 DC working in Hall A