Meeting 2023 01 10
From Hall A Wiki
Revision as of 19:09, 9 January 2024 by Hszumila (Talk | contribs) (Created page with "<span style="font-size:larger">'''GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am'''</span> Link to all previous meetings: [https://hallaweb.jlab.org/wiki/index.p...")
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- BBGEM work completed last month. All UV layers have HV upgrades.
- Need to finish setting up the power supply and write an interface to quickly load HV values (HSV will do this next week)
- Transported the recoil detector, active analyzer into hall.
- Vimukthi and Saru update on the upgrades
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- We plan to swap modules to put the HV inputs on the same side
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Joe B will the GEM LV supply anytime now. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
- Holly, Vimukthi will coordinate with Joe
- Need to verify this week what equipment we need.