GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- RP layers were re-installed vertically in the stand on Monday.
- SBS GEM inline stack removed.
- We decided not to swap modules when routing HV connections
- HV inputs upgraded and tested for layers 7,2&3
- Work is progressing on layers 4&5
- Issue with low-profile GEM shielding, see [3]
- Requested techs to install top sliding rails on the inline stack to resolve the low-profile shielding issue (probably next week).
- Any additional help available will remove the GEM inline cables and lay them out under HCal for re-installation once the new shielded hut is in place.
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Joe B working on LV system.