  • SBS side LV:
    • Joe to connect, instruct on controls (DONE!)
    • Ellen to install some controller and readback (in progress, working with accelerator)
    • Input the jumpers on the breakout panel (DONE!)
    • Run the cables (in progress, Armen adding connectors)
  • SBS GEMs:
    • Install XW into stack (today?)
    • Finish signal cabling (asap)
    • Connect to HV patches (after HDMI cabling complete)
    • reconnect gas to RP layers (after BB XY work?)
    • techs to install final shielding blocks around the electronics hut
  • BB GEMs:
    • Upgrade the XY HV, re-install (would like to have SBS troubleshooting going on at the same time so as not to hold this up)
  • Readout:
    • Balance VTP fibers amongst crates to optimize (after GEMs are installed)
    • Ensure that reboot/troubleshooting script works for all crates (DONE!)
  • High voltage:
    • Finish channels in GUI (DONE!)
    • replace small screws on radial connectors? (optional)
    • move HV to working reboot strip (done, but need to add to gui)
    • finalize script for GUI upload of HV and operation (DONE!)
    • probably need to add command to clear errors
  • Update the documentation on the HV and LV operations (before beam)
  • GEM experts on call (setup before beam)