Remaining GEn-RP install tasks
From Hall A Wiki
- SBS side LV:
- Ellen to network for browser access (in progress)
- SBS GEMs:
- techs to install final shielding block around the electronics hut
- Finish cabling, low level testing, cosmics (in progress)
- BB GEMs:
- Finish cabling, low level testing, cosmics (in progress)
- Update the documentation on the HV and LV operations (before beam)
- GEM experts on call (in progress)
- Clean up our areas: move our stuff out of the Hall (in progress)
- Update channels in the alarm handler
- High voltage cables?!