Start up run plan
From Hall A Wiki
Revision as of 16:34, 26 September 2010 by Jroche (Talk | contribs) (New page: Back to DVCS<br> Back to Daily_Run_Plan <br> <hr> Last update: Sunday 09-26-2010 '''Absolute best-case scenario:''' *Monday 09-27-2010: DAY shift ** start cooling magnets *Monday...)
Back to DVCS
Back to Daily_Run_Plan
Last update: Sunday 09-26-2010
Absolute best-case scenario:
- Monday 09-27-2010: DAY shift
- start cooling magnets
- Monday 09-27-2010: SWING (or late-Day)
- lockup
- hot checkout (MCC)
- start threading beam to the Hall
- Tuesday 09-28-2010: OWL
- start commissioning
Beam without any cryo and no target
We will start with a 5 passes beam.
- Getting beam threaded down to the dump for the first time
- Beam quality optimization study
Goal: optimize beam quality to limit noise in calorimeter
Need: working Compton photon detector with appropriate HV and threshold settings, working Compton DAQ that can provide scaler data to the appropriate EPICS channel (contact: Eric Fuchey for Compton, Jay, MCC support for beam manipulation)
- BCM calibration
Goal: calibrate BCM readings between 0 and 20 uA, with special care to readings between 2 and 7 uA
Need: to follow MCC procedure (MCC-PR-04-008), Hall DAQ working with some random counts (check conditions)
Contact: J. Roche
- BPM calibration
Goal: check response of the BPMs to know motion of the beam Need: Harps working