E08-014 Run Plan

From Hall A Wiki
Revision as of 14:25, 21 March 2011 by Solvigno (Talk | contribs) (1st phase: Helium-4 and Deuterium running)

Jump to: navigation, search

Reconfiguration and Commissioning

  • Starting on April 18 at 8am:
 - Energy change: 4 pass --> 3 pass (8 hours)
 - Beam energy measurement (2 hours)
 - Change DAQ to two independent DAQs (10 hours)
 - Initial checkout (8 hours)
 - BCM calibration (1 hour)
 - Boiling study on 4He and deuterium (2x4 hours)
 - Rate-dependence tests (4 hours)

1st phase: Helium-4 and Deuterium running

The time listed is the total time needed. It should be divided by two if the kinematics point is taken simultaneously by the the two HRSs.

Total time needed: 156.6 hours/2 = 78.3 hours per HRS (production) + 3.5 hours (optics) + (target motion) + (HRS change)

Kin Ein [GeV] Po (GeV) Theta x-region Q^2-range Target I (uA) prescale time(hrs) total time
1 3.356 3.155 16 2N + 3N SRC 0.79-0.85
4He
Carbon
2H
dummy
optics
84
100
60
40
?
13
9
9
?
1
1.6
0.8
4.1
0.3
0.5
6.8 + 0.5
2 3.356 3.110 18.5 2N + 3N SRC 1.04-1.12
4He
Carbon
2H
dummy
optics
84
100
60
40
?
1
1
2
?
1
2.1
0.8
3.7
0.4
0.5
7.0 + 0.5
3.1 3.356 2.905 21.0 2N SRC 1.25-1.34
4He
Carbon
2H
dummy
optics
100
84
60
40
?
3
2
3
?
1
2.0
1.1
5.4
0.4
0.5
8.9 + 0.5
3.2 3.356 3.055 21.0 3N SRC 1.31-1.41
4He
Carbon
dummy
84
100
40
1
1
1
1.3
1.0
0.3
2.6
4.1 3.356 2.855 23.0 2N SRC 1.47-1.58
4He
Carbon
2H
dummy
optics
84
100
60
40
?
1
1
1
1
1
1.7
1.4
4.4
0.3
0.5
7.8 + 0.5
4.2 3.356 3.035 23.0 3N SRC 1.56-1.68
4He
Carbon
dummy
84
100
40
1
1
1
2.6
2.0
0.5
5.1
5.1 3.356 2.795 25.0 2N SRC 1.70-1.82
4He
Carbon
2H
dummy
optics
84
100
60
40
?
1
1
1
1
1
3.4
2.8
8.4
0.7
0.5
15.3 + 0.5
5.2 3.356 2.995 25.0 3N SRC 1.82-2.00
4He
Carbon
dummy
84
100
40
1
1
1
5.2
4.1
1.0
10.3
6 3.356 2.885 27.0 3N SRC 2.04-2.18
4He
Carbon
dummy
optics
84
100
40
?
1
1
1
1
10.4
8.2
2.1
0.5
20.7 + 0.5
7 3.356 2.835 29.0 3N SRC 2.30-2.47
4He
Carbon
dummy
optics
84
100
40
?
1
1
1
1
18.1
14.3
3.6
0.5
36.0 + 0.5
8 3.356 2.790 31.0 3N SRC 2.58-2.77
4He
Carbon
dummy
optics
84
100
40
?
1
1
1
1
18.1
14.4
3.6
0.5
36.1

Target switch: 3 days down

  • Starting on April ? at 8am:
 - Boiling study on 3He (4 hours)
 - Rate-dependence tests (4 hours)
 - BCM calibration (1hour)

2nd phase: Helium-3 and Calcium running

The time listed is the total time needed. It should be divided by two if the kinematics point is taken simultaneously by the the two HRSs.

Kin Ein [GeV] Po (GeV) Theta x-region Q^2-range Target I (uA) prescale time(hrs) total time
1 3.356 3.155 16 2N + 3N SRC 0.79-0.85
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
7
9
5
5
?
3.0
0.8
1.3
1.3
1.0
 ?
2 3.356 3.110 18.5 2N + 3N SRC 1.04-1.12
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
3.6
0.8
2.2
2.3
1.1
 ?
3.1 3.356 2.905 21.0 2N SRC 1.25-1.34
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
2
2
1
1
1
3.6
1.1
4.1
1.8
1.9
1.1
 ?
3.2 3.356 3.055 21.0 3N SRC 1.31-1.41
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
4.5
1.0
2.8
2.9
1.4
 ?
4.1 3.356 2.855 23.0 2N SRC 1.47-1.58
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
4.5
1.4
4.5
4.7
1.4
 ?
4.2 3.356 3.035 23.0 3N SRC 1.56-1.68
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
9.0
2.0
5.5
5.7
2.7
 ?
5.1 3.356 2.795 25.0 2N SRC 1.70-1.82
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
9.0
2.8
8.9
9.4
2.7
 ?
5.2 3.356 2.995 25.0 3N SRC 1.82-2.00
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
18.0
4.1
11.1
11.6
5.4
 ?
6 3.356 2.885 27.0 3N SRC 2.04-2.18
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
36.0
8.2
22.3
23.1
10.8
 ?
7 3.356 2.835 29.0 3N SRC 2.30-2.47
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
63.0
14.3
38.8
40.3
18.9
 ?
8 3.356 2.790 31.0 3N SRC 2.58-2.77
3He
Carbon
Ca-40
Ca-48
dummy
84
100
40
40
40
1
1
1
1
1
63.0
14.4
38.8
40.3
18.9
 ?