July 23rd 2021
From Hall A Wiki
- Updates
- HCAL
- All cable trays installed
- Started cabling
- Bigbite shower
- replaced FADC, second one given to Bill Gunning
- Jessee set up cable tray on blue racks, ready to start cabling. Bringing cable on side and will lift cables
- All FADC cables plugged, cabling trigger cables now ( will ask help from Mark )
- BNC cables FE bunker left and BB shower preshower to FE, Jessee working on alignement will cable when he is done, will start cable to bunker
- HV :
- Scalers : 2 scalers from Bob, need to install in hodoscope crate or in scaler crates
- Cosmics counters : in EEL 122 ready to be moved to Hall A - 1 paddle on top of BB - need find a way to secure on - 2nd paddle on floor - need to figure out how to work
- BB Hodoscope
- software work : comparing new software with older code - looks ok
- not started cabling yet : need training, will start on Monday
- GRINCH
- finished scripts to be used to monitor during run - ADC calibration script and event display -
- cabling out from basket, BNC cables shared with hodoscope - might need to take everything out - TDC conduits can be installed - path need to be refined depending where repeater rack is going
- when cardboard can be removed ? Bradley will check with Jessee
- LHRS
- Maria finished cabling for A1, will check with the DAQ
- 8 or 9 FADCs deployed
- CDet
- issues with HV crate, working now
- taking data right now
- when computer crash - HV setting get lost - might consider switching to Lecroy HV
- need 4x4 MAPMT spares - might need to order new ones - using PMTs from last module
- Bigbite GEM
- connected GEMS to MPPs
- run fiber to bunker a bit short
- will start reading out with SSP
- might reposition the rack
- move computers in Hall ? Need a table ( will check Jack )
- SSP setup in INFN : not working yet but in progress
- VTP readout : Bryan finishing up adding ROC to VTP for VTP readout of MPD - working on library to VTP, just need to combine read-out - can configre MPD and APV through VTP - still need work on readout - ~ 1 week
- UVA GEMs
- SBS side XY : 2 out of 40 chambers shielded - 2 more students helping
- BB side : XY layer cabled in Hall A, Sean working on DAQ.
- 3 slots - Paolo found issue with some line - not terminated properly - , add two termination resistors near connector - send schematics - possibility to get a new a set of backplane
- MPDs order in : FPGA are delay but we have - 1 oscillator part -
- APVs ?
- GEM installation : crane going away August 8 or 9th, trying to see how manny layers can be ready and instrumented
- SBS GEMs might be hold
- any help useful : email Holly if you can help
- GEM will be in Hall and need to decide how to install
- Helicity
- still working in test lab
- no scaler helicity class in Podd, looking at fastest way to integrate in Podd ( hcana has one ? Steve )
- old TG0Helicity class based on ADC
- need to check with Brad and Alex, with channels would go in scalers
- Beamline
- met with Don Jones and Cameron, revive alarm handler for beamline
- new Hall A website live, if anything missing check with David
- HCAL
- On-going tasks
- Network setup
- Scaler crate setup
- 3 rd GEM VXS crate install router moved up ( done )
- detector accounts setup
- boot VME controllers
- detector cabling
- new MPD production - check with Paolo
- MPD VTP readout
- Bigbite - HCal trigger setup
- TS setup
- Beamline crate setup
- HCAL cabling
- Mark hodoscope trigger
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC
- SD delay :
- need to adjust for HCAL transit time with different PMTs
- status of cosmics paddles
- GEM fibers too short : will order 60 m ones