May 28th 2021

From Hall A Wiki
Jump to: navigation, search
  • Updates
    • HCal
      • moved in Hall A, took about 4 hours
      • Jessee said move in bunker in a week
      • software : sbs-online will be moved
      • analysis and gui : daq stuff move in adaq, analysis and replay in a-onl account
      • slow control : aslow on adaqsc
    • Bigbite shower
      • detector stack, basket and weldment in Hall
      • 2 front end racks still need to be moved in Hall
      • Bigbite weldment : weldment cannot go in bunker, individual racks will be moved one by one. Patch panels and cables need to be disconnected. Electronics can stay in the racks. Will help move racks in bunker
      • tedbbdaq : in Holly's office
      • analysis : cosmics analysis from Provokar, still looking at data
      • new cable trays will be added by Jessee
    • GRINCH
      • not sure if gas rack moved yet
      • computer with GRINCH software : will set in office
      • get everything set up on adaq and a-onl
    • LHRS
      • progress on detector
      • will need to get stuff from RHRS
      • network switch rebooted and rpi8 rebooted HV working
    • CDet
      • working with new undergrads, only remote work
      • finishing efficiency analysis of previous module; continuing PMT charge normalization on current module.
      • Steve Wood starting to put HV on EPICS CAEN527 ( might not be required for first run ), might have a few spares
      • most likely installed for GEp
      • might plan to switch to Lecroy
      • new CAEN crate available at CNU
    • BB GEM / INFN
      • moved in Hall
    • INFN GEM
      • hardware work next week
      • will look into DAQ update to optical readout
    • UVA GEM
      • working on shielding


  • Need cryptokey to acess hallgw