GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
- BBGEM work completed last month. All UV layers have HV upgrades.
- Need to finish setting up the power supply and write an interface to quickly load HV values (HSV will do this next week)
- Transported the recoil detector, active analyzer into hall.
- Vimukthi and Saru update on the upgrades
- Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
- Work on SBS GEM is 15 days until Feb 15.
- We plan to swap modules to put the HV inputs on the same side
- Build the SBS GEM bunker after the SBS and HCAL moved into position.
- Joe B will the GEM LV supply anytime now. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
- Holly, Vimukthi will coordinate with Joe
- Need to verify this week what equipment we need.