Wednesday, December 4, 2019, 11:00 EST
From Hall A Wiki
Back to Main Compton Page >> Compton Meetings
*********BLUEJEANS CALL-IN INSTRUCTIONS********* ---------------------------------------------------- 1. Dial Toll-Free Number: 1-888-240-2560 (U.S. & Canada) 2. International participants dial: Toll Number: 1-408-740-7256 3. Enter meeting ID:140287970 Desktop sharing: https://bluejeans.com/140287970
Contents
Agenda
Meeting room = Cebaf Center F227
General
- Still need survey report for laser table --> update BPM offsets
Electron detector
- Detector status
- work on noise with Jinlong, maybe one bad board was causing problem, a few hot strips but most rates disappear with high threshold
- added additionnal network switch
- added network scope of analog signal
- web cam for detector motion and dark current readout
- not sure if we can fix the hot strips easily, needs to decable both side at the same time
- to do
- test FSD with magnets on
- shielding scope / switch
- From Dave estimates at 2.2 GeV : Compton Edet 14.8 mm, zero crossing 7.6 mm ( I think we can go as close as 5 mm from beam, so expect about 40 strips for Compton signal
- QWAD adapter boards
- Counting DAQ
Laser
- Cavity status
- DOCP in cavity
Photon Detector
- CREX preparations
Analysis
- Too busy for analysis!
Minutes
- General
- Hall C will not be ready for spin dance Friday. The soonest Hall C can support the RF stress test is Friday.
- Survey of Laser table not available yet. Once it's available, update BPM offsets.
- Electron Detector
- Most of the strips are "working", noise seems under control. Only 2 planes working right now. Ben needs to develop firmware to use all 4 planes.
- Adaptor boards are on their way with Michael.
- Have 2 good QWADs and we need 2 more. Will wait to see good output before cannibalising the Hall C system.
- Counting DAQ. Using VTP now. Working on timing and scalers using noise signals. Concern about correlated noise.
- Laser
- Locked a couple of days ago. Remote realignment was necessary, gain was the same but there was less input power. Total of 1.9-2.0 kW stored power. When the laser is first turned on there is about 800 mW which drifts down by ~10% over ~20 minutes.
- DOCP. Ideal solution in the cavity is close to minimum returning power.
- Photon Detector
- Completed last linearity test for the moment. Done at 100%, 90%, 70% and 50% of the expected gain. Relatively insensitive to gain (0.85% to 1.15% but not smoothly.) Nonlinear "dark delta" correction applied.
- Could the "dark delta" be gain dependent?
- Timing diagram. Need more information to connect the diagrams. Include HAPPEX timing board.
- Completed last linearity test for the moment. Done at 100%, 90%, 70% and 50% of the expected gain. Relatively insensitive to gain (0.85% to 1.15% but not smoothly.) Nonlinear "dark delta" correction applied.
- Analysis
- Online analysis for CREX needs a location. Copy the main analysis and move to the PREX partition.