Difference between revisions of "E12-17-004-ERR-29May2019"

From Hall A Wiki
Jump to: navigation, search
(E12-17-004 Experimental Readiness Review 2019)
(Agenda)
Line 13: Line 13:
  
 
== Agenda ==
 
== Agenda ==
 +
 +
* (30) Executive Session
 +
* (5) Remarks from Chair and Charge
 +
* (20+10) Charge Items 1, 5, 6: General overview, new equipment (beyond those in common with E12-09-019), and impact and integration with E12-09-019 run plan
 +
* (20+10) Charge Items 1, 5--8: Apparatus ownership, maintenance and control, safety documentation and procedures
 +
* (20+10) Charge Item 2, 2e, 6: E12-09-019 specific hardware, completion/commissioning schedule and tasks
 +
** (20+10) Charge Item 2a: GEMs and associated electronics
 +
** (20+10) Charge Item 2b, 2d: Charge-Exchange polarimetry hardware
 +
** (20+10) Charge Item 2b, 2d: Large Angle polarimetry hardware
 +
* (20+10) Charge Item 3a, 3b, 4: Simulation, analysis software and publication timeline
 +
* (20+10) Charge Item 2c: Mechanical design, engineering
 +
* Executive Session
 +
* Close Out
 +
 +
== Document Drafts ==
 +
* [[Media:E12-17-004_COO.pdf|Conduct of Operations (COO)
 +
* [[Media:E12-17-004_ESAD.pdf|Experiment Safety Assessment Document (ESAD)
 +
* [[Media:E12-17-004_RSAD.pdf|Radiation Safety Assessment (RSAD)

Revision as of 21:10, 28 April 2019

E12-17-004 Experimental Readiness Review 2019 (Hall A)

Time and Location

  • Date: May 29, 2019
  • Location: CEBAF Center Room L102
  • ERR Charge: ERR Charge
  • ERR Committee: Howard Fenker (chair), Lubomir Pentchev, Chris Cuevas, Pavel Degtiarenko, Bert Manzlak, Ed Folts (observer), Javier Gomez (observer)

Agenda

  • (30) Executive Session
  • (5) Remarks from Chair and Charge
  • (20+10) Charge Items 1, 5, 6: General overview, new equipment (beyond those in common with E12-09-019), and impact and integration with E12-09-019 run plan
  • (20+10) Charge Items 1, 5--8: Apparatus ownership, maintenance and control, safety documentation and procedures
  • (20+10) Charge Item 2, 2e, 6: E12-09-019 specific hardware, completion/commissioning schedule and tasks
    • (20+10) Charge Item 2a: GEMs and associated electronics
    • (20+10) Charge Item 2b, 2d: Charge-Exchange polarimetry hardware
    • (20+10) Charge Item 2b, 2d: Large Angle polarimetry hardware
  • (20+10) Charge Item 3a, 3b, 4: Simulation, analysis software and publication timeline
  • (20+10) Charge Item 2c: Mechanical design, engineering
  • Executive Session
  • Close Out

Document Drafts

  • [[Media:E12-17-004_COO.pdf|Conduct of Operations (COO)
  • [[Media:E12-17-004_ESAD.pdf|Experiment Safety Assessment Document (ESAD)
  • [[Media:E12-17-004_RSAD.pdf|Radiation Safety Assessment (RSAD)