== Priority Items ==
 
== Priority Items ==
 
<s>Hall A Moller Polarimeter target magnet testing (Simona's turn when she's ready, and any fixes afterward if necessary)</s> Finally done! :D Everything is working and ran up to full current without issue.
 
  
 
Install S0 counter above BB for a cosmics trigger.
 
Install S0 counter above BB for a cosmics trigger.
 
Locking bar for the Right Shield House (needs to be installed and demonstrated it will keep door closed)
 
  
 
Jumper bars for SBB coils (in progress)
 
Jumper bars for SBB coils (in progress)
Line 14: Line 10:
  
 
Connect magnet leads for SBB corrector magnets (2 AWG welding cable) (cables run, Reagan is making final connections)
 
Connect magnet leads for SBB corrector magnets (2 AWG welding cable) (cables run, Reagan is making final connections)
 
re-install ground fault detector in LQ1 supply - requires configuration of module (not started)
 
 
Gas manifolds for GEM gas cylinders (started)
 
 
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
 
 
Gas mix controller and MFCs for GEM detectors (not started)
 
  
 
Readout for LCW pressure sensors added at end of beamline walkway (not started)
 
Readout for LCW pressure sensors added at end of beamline walkway (not started)
Line 27: Line 15:
 
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (Done, needs tested)
 
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (Done, needs tested)
  
Install thermistors on SBS/Big Bite magnets and junction boxes. <s>ADC node boards made and parts stuffing is ongoing.</s> Should have enough boards now. Software is basically done, but will need to be updated after all thermistors are in place.
+
Install thermistors on SBS/Big Bite magnets and junction boxes. Software is basically done, but will need to be updated after all thermistors are in place.
  
 
Install Klixons on SBB and connect to power supply.
 
Install Klixons on SBB and connect to power supply.
  
<s>Install Klixons on BB and connect to power supply.</s> Done.
+
Test LQ2 FuG with new polarity reversal switch.
  
<s>Rpi for threshhold monitoring for DAQ</s> Done.
+
Find and connect NMR cables in CH
  
Test LQ2 FuG with new polarity reversal switch.
+
Mount Left Shield House temperature readout in CH
  
Verify LQ2 has LCW reconnected.
+
Find video cables from hall in the CH
  
 
== Would Be Good To Do Items ==
 
== Would Be Good To Do Items ==
  
 
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker
 
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker
 +
 +
Gas manifolds for GEM gas cylinders (started)
 +
 +
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)
 +
 +
Gas mix controller and MFCs for GEM detectors (not started)
  
 
Roofing material for SBS GEM bunker (located some possible material - will run past Jessie)
 
Roofing material for SBS GEM bunker (located some possible material - will run past Jessie)
Line 52: Line 46:
  
 
Swap out MFCs in VDC mixing system
 
Swap out MFCs in VDC mixing system
 
Remove three Oxford power supplies from HMS
 
  
 
HMS/SHMS Heater and fan changes, fixes, upgrades etc.
 
HMS/SHMS Heater and fan changes, fixes, upgrades etc.

Revision as of 19:12, 27 September 2021

Priority Items

Install S0 counter above BB for a cosmics trigger.

Jumper bars for SBB coils (in progress)

Controls for SBB and corrector coils (waiting for water to the magnets)

Install magnet leads for SBB (535 MCM cable) (cables run, waiting on copper bus bars) (connections still need to be torqued)

Connect magnet leads for SBB corrector magnets (2 AWG welding cable) (cables run, Reagan is making final connections)

Readout for LCW pressure sensors added at end of beamline walkway (not started)

Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors (Done, needs tested)

Install thermistors on SBS/Big Bite magnets and junction boxes. Software is basically done, but will need to be updated after all thermistors are in place.

Install Klixons on SBB and connect to power supply.

Test LQ2 FuG with new polarity reversal switch.

Find and connect NMR cables in CH

Mount Left Shield House temperature readout in CH

Find video cables from hall in the CH

Would Be Good To Do Items

Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker

Gas manifolds for GEM gas cylinders (started)

Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) (not started)

Gas mix controller and MFCs for GEM detectors (not started)

Roofing material for SBS GEM bunker (located some possible material - will run past Jessie)

Remove actuators from right arm magnets. (Dipole complete)

clean up R-arm supply platform

clean up L-arm supply platform

Swap out MFCs in VDC mixing system

HMS/SHMS Heater and fan changes, fixes, upgrades etc.

PARTS ORDER LIST FOR 1 OCT

-2 wire cable, ferrules, \# 6 hardware

Possible Future Items

Replace air compressor in Hall A Gas Shed (on hold till next fiscal year)

Remote reset for Hall C spectrometer motion (maybe next year)

Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (need Steven).