− | + | == Priority Items == | |
− | + | Hall A Moller Polarimeter target magnet re-install: target install and survey, compressor and chiller clean up and setup, testing | |
− | + | Low voltage connections for BB detectors | |
− | + | Controls for SBB and corrector coils | |
− | + | Re-tap the SBB supply main transformer for full power | |
− | + | Connect 480VAC for SBB and corrector power supplies | |
− | + | Install magnet leads for SBB (535 MCM cable) | |
− | + | Install magnet leads for SBB corrector magnets (2 AWG welding cable) | |
− | + | Connect SBB and corrector magnets to FSD | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
re-install ground fault detector in LQ1 supply - requires configuration of module | re-install ground fault detector in LQ1 supply - requires configuration of module | ||
Line 25: | Line 21: | ||
connect power and LCW to BB supply on R-arm platform | connect power and LCW to BB supply on R-arm platform | ||
− | + | Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (Steve). | |
− | + | Gas manifolds for GEM gas cylinders | |
− | + | Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller) | |
− | + | Gas mix controller and MFCs for GEM detectors | |
− | + | Readout for LCW pressure sensors added at end of beamline walkway | |
+ | |||
+ | Re-install crash buttons in Hall A Counting Room - <s>RQ1 button for BB</s> and new ones for SBS supply and correctors | ||
+ | |||
+ | |||
+ | == Would Be Good To Do Items == | ||
+ | |||
+ | Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker | ||
Remove actuators from right arm magnets. (Dipole complete) | Remove actuators from right arm magnets. (Dipole complete) | ||
− | + | clean up R-arm supply platform | |
− | + | clean up L-arm supply platform | |
− | + | Swap out MFCs in VDC mixing system | |
− | + | Remove three Oxford power supplies from HMS | |
− | + | Heaters for SHMS magnet flags./ Guard modifications complete, waiting on controller | |
− | + | Heaters for HMS magnet flags-Heaters, modifications to guards complete, heaters installed. Waiting on controller. | |
− | |||
− | |||
− | + | == Possible Future Items == | |
− | + | Replace air compressor in Hall A Gas Shed (on hold till next fiscal year) | |
− | + | Remote reset for Hall C spectrometer motion (maybe next year) |
Revision as of 14:36, 14 August 2021
Priority Items
Hall A Moller Polarimeter target magnet re-install: target install and survey, compressor and chiller clean up and setup, testing
Low voltage connections for BB detectors
Controls for SBB and corrector coils
Re-tap the SBB supply main transformer for full power
Connect 480VAC for SBB and corrector power supplies
Install magnet leads for SBB (535 MCM cable)
Install magnet leads for SBB corrector magnets (2 AWG welding cable)
Connect SBB and corrector magnets to FSD
re-install ground fault detector in LQ1 supply - requires configuration of module
connect power and LCW to BB supply on R-arm platform
Install new liquid level meters on SHMS- Install done, waiting on software and LN2 probe cal to go live (Steve).
Gas manifolds for GEM gas cylinders
Nitrogen supply for GEM gas cylinder valves (Clippard valves and cylinder controller)
Gas mix controller and MFCs for GEM detectors
Readout for LCW pressure sensors added at end of beamline walkway
Re-install crash buttons in Hall A Counting Room - RQ1 button for BB and new ones for SBS supply and correctors
Would Be Good To Do Items
Re-locate NDX detectors in Hall A - one in DAQ bunker and the other in BB GEM bunker
Remove actuators from right arm magnets. (Dipole complete)
clean up R-arm supply platform
clean up L-arm supply platform
Swap out MFCs in VDC mixing system
Remove three Oxford power supplies from HMS
Heaters for SHMS magnet flags./ Guard modifications complete, waiting on controller
Heaters for HMS magnet flags-Heaters, modifications to guards complete, heaters installed. Waiting on controller.
Possible Future Items
Replace air compressor in Hall A Gas Shed (on hold till next fiscal year)
Remote reset for Hall C spectrometer motion (maybe next year)